Beacon how-to · November 2026
Planner and Coverage
The Labor Planner is where you decide which order runs on which line, on which day, and for how long. Coverage tells you if the stock is there to build those orders. These seven how-tos walk through both, step by step. They are for leads, line captains and coordinators.
Screenshots are from Beacon's test site. The orders QA-2101 and QA-2102, the lines and all numbers are demo data. Item numbers and names are replaced with demo values.
1. How to plan the week
Who: Admin or Coordinator. When: once a week, before the week starts, and any time the orders change.
Before you start
- The orders must already be in Build Schedule with a due date.
- The tray only shows orders due in the week you are planning. Orders due the week after do not show up until you move to that week.
Steps
- Go to Build Schedule and click the Labor Planner tab.
- Use the arrows next to the date to go to the week you want. The week runs Monday to Sunday.
- Click a day name to open that day. Place your orders on it (see how to plan a day).
- Repeat for each day you will run.
- Click Save plan. Wait until the button says Saved.
- Click Week to go back to the week. Check the tiles at the bottom: Total units, Week hours, Headcount required and Peak day crew.
- To see it by line instead of by day, click Lanes next to Days. Each line is a row and each day is a column.


If something goes wrong
- The Save plan button stays red. Your plan is not saved yet. Click it again and wait for Saved.
- A yellow banner says blocks are stacked or past the end of the day. See the Known issue in how to plan a day.
- You cannot see Friday to Sunday in the Lanes view. Scroll the table sideways. On a smaller screen only Monday to Thursday fit.
- The page spins and never loads. Reload the page once.
2. How to plan a day by dragging orders from the tray
Who: Admin or Coordinator. When: when you place orders on lines for a day.
Before you start
- Open the day first: click the day name in the week.
- A lane is one line. The numbers H0, H1, H2 and so on are hours from the start of the shift. A 7.25 hour shift ends at H7.25.
Steps
- Look at the Order Tray on the left. It lists the open orders and how many units are left to plan.
- Press on an order tile and drag it to a lane. Let go at the hour where you want it to start.
- A bar opens at the bottom. It shows the Window (start and end), the Hours, This block (units) and the Running total for the order.
- If it looks right, click Place block. To back out, click Cancel.
- Check the tray. The units left for that order go down by the size of the block.
- Click Save plan at the top.



If you drop an order so that it would run longer than the shift, Beacon cuts it at the end of the shift, or where the next block starts. You do not have to measure it yourself.
If something goes wrong
- The tile will not drop. Drop it on the lane bar itself, not on the lane name. Hold the mouse down until you reach the lane.
- The tray tile says PARTIAL when nothing is planned. This is only a label. The units left number is the one to trust.
- The block is shorter than you wanted. It hit the end of the shift or another block. Move the other block first, or use another lane.
- The order you want is not in the tray. The tray shows orders due that week. Turn on Show all open orders to see the rest.
3. How to move, shorten or remove a block
Who: Admin or Coordinator. When: the plan changed after you placed a block.
Steps to move a block
- Press on the bar and drag it left or right on its lane, or to another lane.
- Let go. The block lands at the new time.
- Click Save plan.
Steps to shorten a block
- Drag the right edge of the bar to the left. The block gets shorter and the units go back to the tray.
- Or open the block (next steps) and type a smaller number in Qty.
- Click Save plan.
Steps to open the block panel
- Click the block to pick it. A red cross shows on the corner.
- Press Enter on your keyboard. The panel opens at the bottom.
- Change Qty, or use one of the buttons: Remove block, Split, Roll balance to next day, Fill week on this line, Roll to next week. Click Done when finished.

Steps to remove a block
- Open the block panel as above.
- Click Remove block. The units go back to the tray.
- To clear a whole day, click Clear day above the lanes. To clear the whole week, click Clear week and confirm.
- Click Save plan.
If something goes wrong
- The panel does not open when you click. Click the block once to pick it, then press Enter. Pressing Enter a second time closes it.
- The lane shows red hours “over”. The block runs past the end of the shift. Lower the quantity or move it earlier.
- You removed the wrong block. Place it again from the tray. Nothing is saved until you click Save plan, so you can also reload the page to start over.
4. How to roll the balance to the next day
Who: Admin or Coordinator. When: a day is full and part of the order is left over.
Steps
- Open the block panel (click the block, press Enter).
- Click Roll balance to next day.
- Read the message. It says how many units went to the next day, on which line, and how many are still to plan.
- To spread all the rest across the week on the same line, click Fill week on this line instead.
- To move the rest to next week, click Roll to next week.
- Click Save plan. The message says to save, and the new block is not kept until you do.
905 units on Fri 4B, 714 still to plan. Friday now has a 905 unit block on lane 4B (7.24 hours). 1,619 − 905 = 714 left in the tray. In the week view Friday shows 905 units (see Fig. 1).
If something goes wrong
- Only part of the balance moves. A day only holds one shift. The rest stays in the tray. Click the button again from the Friday block, or use Fill week on this line.
- You do not see the new block. It went to the next day. Click the next day name to see it.
- You closed the page before saving. The rolled block is lost. Do the roll again and save.
5. How to read the crew and headcount warnings
Who: Admin, Coordinator, Lead. When: after you place blocks, to check you have enough people.
Steps
- Open the day in the planner and scroll down to Crew Check – Staffing.
- The big number is the people you need at the busiest moment of the day. It also says which hour that is, for example H1.
- Read the line under it. It says how many people are fixed on the shift no matter what is built (line captains, material handlers, QA / gate keepers).
- Look at the table The day by role. For each role it shows the people and the hours.
- Read Running at the peak at the bottom. It lists which lanes and orders are running at the busiest moment.
- Back in the week view, check the Peak day crew and Headcount required tiles.

The people column does not add up to the big number. Each role shows its own busiest moment. Hours are people times time on the job. In the example 12 × 6.25 + 13 × 6.25 = 156.25 hours of assemblers, shown as 156.2.
If something goes wrong
- The crew number is higher than you expect. Two blocks may overlap on one lane, or two lanes run at the same time. Move one so they do not overlap. Also see the Known issues in how to plan a day and how to move a block.
- A yellow banner says blocks are stacked. Two blocks overlap, so their crews are counted twice. Move one of them.
- The line seems to need more people than you have. Move work to another day. Do not change the numbers on paper to make them fit.
6. How to read Coverage and find a shortfall
Who: Admin, Coordinator, Lead. When: before you commit a week, to see if the stock is there.
Before you start
- Only orders due next week or later use stock in Coverage. Orders due this week are left out.
- Stock only counts if it still has enough shelf life left. The screen says how many days (here 220).
Steps
- Go to Build Schedule and click the Coverage analysis tab.
- Read the cards at the top: Scheduled builds, Can build, Short, Missing BOM and Inventory Coverage.
- Look at the table. Each row is one order. Read across.
- Click the small arrow on the left of a row to open it. It lists every part the order needs.
- Find the red dots. Those are the parts holding the order back. Read the Reason on the right.
What each column means
| Column | What it tells you |
|---|---|
| PO | The order number. |
| Material | The product you are building. |
| Scheduled | Units you plan to build. |
| Buildable | Units the stock can support right now. |
| Status | Can build, or Short with how many units are missing. Under it, short runningis the total short so far, counting the earlier orders in the list. |
| Limiting child | The part or parts that hold the order back. |
When you open a row, the columns are:
| Column | What it tells you |
|---|---|
| Child | One part (a box, a bag, a candy). A red dot means it is short. |
| Needed | How much the order needs. The small line under it is the sum, for example 2,400 × 13.2. |
| Available | How much stock you can use. |
| Short | Needed minus available, when it is short. |
| Reason | Why it is short. See below. |
What each reason means
| Reason | Meaning and what to do |
|---|---|
| No stock on hand | The part is not in the stock file. Check the part is really not in the building and upload fresh stock if it is. |
| N cs on hand · no expiration date in the file | There is stock but the file has no date, so Beacon cannot count it. Fix the date column in the stock report. |
| N cs on hand · none with N+ days left | There is stock but it is too close to its date. It does not count. |
| Not enough stock | Some stock counts, but not all you need. |
| Consumed by earlier builds | An order higher in the list uses the stock first. |
| No recipe / BOM | The product has no parts list. Add one in Material Master. |
| No pack spec / pieces-per-case | Beacon cannot turn pieces into cases. Fill in the pieces per case. |
| Override | Someone set the quantity by hand, or marked it always available. |


No stock on hand. QA-2102 is 1,200 units, also short. The running total is 2,400 + 1,200 = 3,600.
300 cs on hand · no expiration date in the file, not
No stock on hand(Fig. A). When several parts hold the order back, the reason names its part first, for example
DEMO-C1: 400 cs on hand · none with 220+ days left. Open the row to see every part.

If something goes wrong
- An order is missing from Coverage. It is due this week. Coverage only counts orders due next week or later.
- The numbers look old. Click Recompute. The line at the top says when stock was last checked.
- Everything says No stock. The stock file may be old or empty. Look at the stock snapshots.
- You want to change Available. Do not guess. Type only a real count. A negative number is refused.
7. How to look at stock snapshots (view only)
Who: Admin, Coordinator, Lead. When: you want to see what stock Beacon is using, and when it was loaded.
Steps
- Go to Build Schedule → Coverage analysis.
- Click Stock upload history. A list opens. Each line has a file name, the date and time, the number of items and how many were left out for short shelf life.
- Click one line. The snapshot opens.
- Use the search box at the top right to find an item, a batch or a bin.
- Click an item row to open it. It shows the bins where the stock sits. The bins add up to the cases on that row.
- Click Back to return to Coverage.


No expiry, 2 bins. You open the row: one bin has 2,000 and the other has 1,966. 2,000 + 1,966 = 3,966. The stock is in the building, but the file has no date. Ask whoever makes the stock report to add the expiration date.
If something goes wrong
- The page says Loading and never ends. Go back to Coverage and click a line in the history again. Do not open the snapshot page without picking a line.
- The item is not in the snapshot. It was not in that report. Try an older snapshot, or ask for a new report.
- The page is blank after you open it. Reload once.