Beacon how-to · November 2026

Build Schedule

The Build Schedule is the list of every order the site has to build: customer orders and non-production jobs. This page shows eight everyday jobs: read the screen, add an order, find one, change its status, close it, load the weekly schedule from a file, export it, and see it on a calendar.

Screenshots are from Beacon's test site. All orders, item numbers and names in them are demo data, not real production data.

1. How to read the Build Schedule

Who: anyone who plans or runs the floor (Coordinator, Lead, Admin). When: at the start of the shift, or any time you ask “what is due this week?”

Steps

  1. Click Production at the top, then Build Schedule. The Customer Orders tab opens.
  2. Look at the tiles at the top: Total Orders, then one tile for each status (In-Process, On-Hold, Closed, Open, Pending / Allocated), then Total Ordered and Total Built. The status tiles always add up to Total Orders.
  3. Under the tiles, pick a tab: This week, Next week or All. The number beside each tab is how many orders are in it. The tiles count exactly the rows in the list: the tab you picked, the Status filter and the search.
  4. Read the rows. Each row shows the Work Order (the PO number), Item, Description, Order Qty, Comments, Materials Status, Work Center and Base UoM.
  5. If a row has a small Planned tag next to the Work Order, the order is already in the labor plan.
Build Schedule. Tiles: Total Orders 22 this week, In-Process 0, On-Hold 0, Closed 0, Open 22, Total Ordered 30,533 units, Total Built 5,305 units. Tabs: This week 22, Next week 0, All 24. The list starts with orders QA-3003 and QA-3002.
Fig. 1Tiles on top, week tabs below them, one row per order. Demo data.

Which week is an order in?

The week comes from the order's Due Date, and a week runs Monday to Sunday.

  • A due date on a Sunday is still in that week. A due date on the next Monday is in Next week.
  • An open order that is already past due stays in This week so nobody forgets it.
  • A closed order that is past due only shows under All.
ExampleToday is Friday, November 6. Order QA-1001 is due Friday, November 6: it is in This week. Order QA-1002 is due Tuesday, November 10: it is in Next week. An order due Sunday, November 8 is still This week; one due Monday, November 9 is Next week. Say This week has QA-1001 with 400 units open, QA-1003 with 300 units on hold and QA-1004 with 250 units closed. Total Ordered is 400 + 300 + 250 = 950; Open shows 1, On-Hold shows 1, Closed shows 1.

If something goes wrong

  • The order you want is not in the list. Check the tab. A past-due closed order is only under All.
  • The list is shorter than you expect. Open Status and make sure all statuses are ticked.
  • Column headings do not sort. Clicking a heading does nothing at the moment. Use the search box to narrow the list instead.
  • Phone screen. On a phone the Add Order and Import buttons can fall off the right edge. Use a laptop or a wide tablet for this page.

2. How to add an order

Who: Coordinator, Lead or Admin. When: a customer order is not on the weekly file, or you need a one-off order or a non-production job (rework, relabel, repack and so on).

Before you startHave the PO number, the item (Material ID), the quantity and the due date ready. Check the list first: if the PO is already there, you do not need to add it again.

Steps for a production order

  1. Click Add Order (top right). The switch at the top of the box says Production Order. Leave it on.
  2. Type the Work Order. Use letters, numbers and hyphens only. Example: QA-1001.
  3. Click Material ID and pick the item from the list. You can type in the list to narrow it. The Description fills in by itself.
  4. Type the Order Qty and the Production Qty. Both start at 0, so change both. Example: 400 and 400.
  5. Check Status (it starts on Open) and pick the Due Date. It starts on today.
  6. Scroll down to Custom Fields. Work Center fills in from the item. Type the Base UoM (the unit, for example CS for cases).
  7. Click Create Order. A short “Order created” message appears and the new row is in the list.
The Add Order box. The Production Order switch is on. Fields: Work Order, Item, Material ID, Description, Order Qty, Production Qty, Status Open, Due Date, Work Date, Assigned Line.
Fig. 2The Add Order box when it first opens.
The Material ID list is open, showing item numbers each with a product name underneath, and a search box at the top.
Fig. 3Pick the item from the Material ID list. Type to narrow it.
The Add Order box filled in: Work Order QA-6001, Material ID 90000015, Description Demo product 16, Order Qty 400, Production Qty 400, Status Open, Due Date November 6th 2026.
Fig. 4Work Order, item, and both quantities filled in.
The bottom of the Add Order box. Work Center shows FLEX, filled in. Base UoM is empty and marked with a star. Cancel and Create Order buttons.
Fig. 5At the bottom: Work Center is filled in, Base UoM is still empty. Type it, then click Create Order.
The list after creating the order. The new row QA-6001, item 90000015, Demo product 16, quantity 400, status Open, work center FLEX, Base UoM CS. The tile Total Orders went up by one.
Fig. 6The new order is in the list and the tiles went up by one.

Steps for a non-production job

  1. Click Add Order, then click the switch at the top so it says Non-Production Order.
  2. Type the Job ID, for example QA-JOB-1.
  3. Pick the Job Type: Rework, Relabel, Repack, Sort, Inspection or Other.
  4. Type the Order Units. Leave Reworked/Completed Units at 0 for a new job.
  5. Set the Status and Due Date, fill in Work Center and Base UoM under Custom Fields, and click Create Order.
The Add Order box with the switch set to Non-Production Order. Fields: Job ID, Job Type, Description, Order Units, Reworked/Completed Units, Status, Due Date, Work Date, Comments.
Fig. 7With the switch on Non-Production, the box asks for a Job ID and a Job Type instead of an item.
ExampleA customer wants 400 cases of one item built by Friday. You click Add Order, type QA-1001, pick the item, type 400 and 400, leave Status on Open, keep today as the Due Date, type CS for Base UoM and click Create Order. The new row shows 400 and Open. Total Orders goes up by 1 and Total Ordered goes up by 400. A pallet holds 27 cases, so the line will need 400 ÷ 27 = 14.8, which rounds up to 15 pallets.
Known issues

After you press Cancel and open Add Order again, the Work Order and quantities you typed before are still there. Clear them before you type a new order. The custom fields do clear.

A quantity of 0 and a due date in the past are both accepted without a warning. Check them yourself before you click Create Order.

If something goes wrong

  • Red text under a box. The box is empty or wrong. A Work Order can only have letters, numbers and hyphens. Quantities must be numbers, not letters and not negative.
  • A pop-up asks you to fill a field. That is Work Center or Base UoM under Custom Fields. Scroll down and fill it.
  • A message says one PO is one item. A PO can only hold one item. Use a new PO number for the second item.
  • A message says the PO already has an open order for this item. That order is already on the schedule. The message gives its status, quantity and due date. Find it and change its quantity with Edit instead of adding it again. If that order is finished, close it first; then you can add the new one.

3. How to find an order

Who: anyone. When: a customer or the line asks “where is PO such-and-such?”

Steps

  1. Click the search box next to the week tabs.
  2. Type part of the PO number, the item number or a word from the description. You do not need the whole number.
  3. Look at the tab counts. They change to show how many matches are in This week, Next week and All.
  4. If the order is not in the tab you are on, click another tab. All shows every match.
  5. To narrow by status, click Status and untick the statuses you do not want. Tick them again when you are done.
  6. To start over, click the small x in the search box.
The search box contains 6001. One order is listed: QA-6001. The tab This week shows 1 and All shows 2. The tiles show 1 order and 400 units.
Fig. 8Typing 6001 narrows the list to one order. The tab counts and tiles follow the search.
ExampleYou type 1002. Order QA-1002 shows up and the Next week tab shows 1, because QA-1002 is due Tuesday. This week shows 0. You click Next week and the order is there.
Known issues

The search box says “PO, DN, model, customer”, but it really searches the PO, item number and description. It does not search the status or the work center. The second Search box inside the table works on the rows you are looking at and not on the tab counts.

When nothing matches, the tiles show 0 and the Export button is greyed out. Clear the search and they come back.

If something goes wrong

  • “No results.” Clear the search and try fewer letters. Check the Status filter too.
  • You see 10 rows only. The table shows 10 rows per page. Use the page arrows under the list.

4. How to change an order's status, put it on hold, or mark it Allocated

Who: Lead, Coordinator or Admin. When: the material is short and you want to hold the order, or the material has been pulled and you want to mark the order Allocated.

Steps

  1. Find the order (see How to find an order).
  2. Click the three dots at the right end of the row. A menu opens with Edit, Close order and Delete.
  3. Click Edit. The order opens in the Edit box. Built Qty is read-only: it comes from the hours people post.
  4. Open the Status list and pick the new status: Open, Pending, Allocated, In Process, Completed, Closed or On Hold.
  5. Scroll to the bottom and click Update Order. The box closes and the tiles move to match.
The row menu is open under the three dots. It lists Actions: Edit, Close order, Delete.
Fig. 9The three dots at the end of the row open the menu.
The Edit Production Order box. Work Order QA-6001, Material ID, Description, Order Qty 400, Production Qty 400, Built Qty read-only 0, Status Open, Due Date.
Fig. 10The Edit box. Built Qty is grey because you cannot type in it.
The Status list is open. It shows Open, Pending, Allocated, In Process, Completed, Closed and On Hold.
Fig. 11The seven statuses.
After the change. The order shows On Hold in Materials Status. The On-Hold tile shows 1 and the Open tile shows 0.
Fig. 12The order now says On Hold. The On-Hold tile went from 0 to 1 and Open went from 1 to 0.

What Allocated does

An order set to Allocated stops drawing down stock on the Coverage screen. Beacon treats the material as already pulled for that order. Use Allocated only after the material is really pulled by hand. If you set it too early, Coverage will show more stock than is really free.

An order set to On Hold keeps its place in the list and is counted in the On-Hold tile. Change it back to Open when the hold is over.

ExampleOrder QA-1001 is Open with 400 units and is short of packaging. You open Edit, pick On Hold and click Update Order. On-Hold goes from 0 to 1, Open goes from 1 to 0, and Total Orders stays the same. When the packaging arrives you edit it again and pick Open. Later the stock is pulled for it, so you pick Allocated. Open goes from 1 to 0 and Pending / Allocated goes from 0 to 1.

If something goes wrong

  • You reopened a Closed order and Beacon refused. The PO already holds a different item. A PO can only hold one item. Add the order again under a new PO number.
  • You cannot change Built Qty. That is on purpose. It comes from the hours people post in the Hour Tracker.
  • The row disappeared after you changed the status. Check the Status filter and the tab. The order may now be in a different tab or hidden by the filter.

5. How to close an order

Who: Lead, Coordinator or Admin. When: the order is done and nothing more will be built for it.

Steps

  1. Find the order and click the three dots at the end of its row.
  2. Click Close order.
  3. Read the message. It says the PO leaves the open orders and the planner's tray, and stops counting against stock.
  4. Click Confirm. (Click Cancel if you changed your mind.)
A box titled Close order. It says PO QA-6001 leaves the open orders and the planner's tray, and stops counting against stock. Buttons Cancel and Confirm.
Fig. 13The Close order box tells you what changes.
After closing. The order shows Closed. The Closed tile shows 1 and Open shows 0.
Fig. 14The row now says Closed and the Closed tile went up by one.
ExampleOrder QA-1001 finished all 400 units on Friday. You click Close order and Confirm. The row stays in the list and says Closed. The Closed tile goes from 0 to 1. The order is gone from the planner's tray and no longer holds back stock on Coverage. If it was due earlier than this week, it now only shows under All.

If something goes wrong

  • You closed the wrong order. Open Edit on it and set the Status back to Open. If another order now holds that PO with a different item, Beacon refuses; add it again under a new PO.
  • You only meant to remove a mistake. Close is for finished work. A row you added by mistake can be removed from the same menu with Delete. Delete cannot be undone, so read the PO number in the box before you confirm.
  • Finished orders from Checkpoint. Closing orders after a Shift Review is done on the Shift Review screen, not here.

6. How to upload the weekly schedule

Who: the person who plans the week (Coordinator, Lead or Admin). When: each week, when the customer sends the new schedule file.

Before you startSave the file as Excel (.xlsx or .xls) or CSV. It needs at least a column for the item (Material ID) and a column for the quantity. A Work Order column and a Due Date column are strongly recommended.

Steps

  1. Click Import Schedule (top right).
  2. Under Schedule file, click Choose File and pick your file.
  3. Look at Column mapping. Beacon fills in the column names it remembers from last time. The line “Columns in this file” shows the real column names in your file. Each box must match one of them exactly.
  4. If a box is wrong, type the exact column name from your file into it. If you will use this file layout every week, click Save mapping to profile so Beacon remembers it.
  5. Look at the Preview table. Check that the item, quantity, work order and due date look right in the first rows.
  6. Click Import. Nothing is written yet. A review screen opens.
  7. Read the review: how many orders are new, updated, removed, kept, unchanged and skipped. Click the small plus to open a list.
  8. If the numbers are what you expect, click Confirm import. If not, click Back or the x and nothing changes.
  9. Look at the Next week tab. Your new orders are there.
Import Schedule, column mapping. Material ID mapped to Item, Quantity to Target Qty, Work Order to Order, Due Date to Due Date, Description to Material Description. A preview table shows one order, quantity 300, work order QA-6101, due 11/10/26. Buttons Save mapping to profile, Cancel and Import (1).
Fig. 15Column mapping and the preview. The Import button shows how many orders will be read.
The review step. It reads: Review what this upload will change. Nothing is written until you confirm. 1 order in the file: 1 new order, 0 updated, 0 removed, 0 kept, 0 unchanged, 0 skipped. Left alone: 12 existing orders due this week or in a week this file does not cover. An upload never changes this week's orders. The new order QA-6101, quantity 300, is listed. Buttons Back and Confirm import.
Fig. 16The review step. It shows what will change before anything is written.
The Next week tab after the import. The new order QA-6101 is listed with status Open. Work Center and Base UoM show a dash.
Fig. 17After Confirm import, the new order is under Next week. Work Center and Base UoM are blank.

What the upload does and does not touch

  • It never changes this week's orders. The review says how many existing orders it left alone. This keeps the plan for this week safe.
  • Orders that are already on the planner are kept: the file's changes go onto the same order, so plans and history stay linked to it.
  • Orders for a week the file does not cover are left alone too.
ExampleThe file has 3 orders for next week: QA-2001 (400 cases), QA-2002 (300) and QA-2003 (250). QA-2002 is already in Beacon with the same 300. The review reads 2 new, 0 updated, 0 removed, 1 unchanged. Before the upload, Next week showed 5 orders. After Confirm import it shows 5 + 2 = 7. This week's number does not change.
Known issues

When you first open the box, before you choose a file, it may show a red “Import blocked” line. That is only because there is no file yet. It goes away when you pick a file with the right column names.

Orders made by an upload can have a blank Work Center and Base UoM (shown as a dash). If you need them, open Edit on the order and fill them in.

If something goes wrong

  • “Import blocked” after you chose a file. The column names in the boxes are not in your file. Compare the boxes with the “Columns in this file” line and fix them.
  • “Could not read file.” The file is empty or is not an Excel or CSV file. Open it yourself and save it again as .xlsx.
  • The review shows orders removed that you did not expect. Do not confirm. Click Back, check the file and the week it covers, and ask a Lead.
  • An order shows a wrong due date. Fix the cell in the file and upload again, or open Edit on the order and change the due date.

7. How to export the schedule

Who: anyone who can open the Build Schedule. When: you need the list in Excel, to check it, share it or work on it.

Steps

  1. Click Export at the top right of the page.
  2. Your browser saves an Excel file (.xlsx). Open it from your Downloads.
  3. Check the file: it has one row per order and 18 columns.

Export writes exactly the rows in the list: the tab, the Status filter and the search. For the whole schedule, click All, tick every status and clear the search first.

ExampleThe screen says This week 22 and All 24. On This week, the file has 22 rows. Click All and export again: 24 rows.

If something goes wrong

  • Export is greyed out. The list is empty: the search or the Status filter matches nothing. Clear the search or tick more statuses.
  • The file is missing orders. Check the tab and the Status filter. The file only has what the list shows.
  • The file has a strange name or will not open. Rename it so it ends in .xlsx, then open it.

8. How to use Calendar View

Who: anyone who plans the week. When: you want to see which orders land on which days.

Steps

  1. On the Build Schedule page, click the Calendar View tab.
  2. Find the order on its day. Each order sits on its Work Date. If it has no Work Date, it sits on its Due Date.
  3. Use the arrows to go back or forward. Click Today to come back to the current day.
  4. Pick Month, Week or Day to change how much you see.
  5. Click All Statuses to show only the statuses you want.
  6. Click an order to open its details: Work Order, Status, Order Type, Order Qty, Built Qty, Due Date and Description.
  7. Click Edit Order in the details box to change it, or Close to go back to the calendar.
Calendar View for November 2026, Month view. The week starts on Sunday. An order QA-6001 sits on Friday the 6th. The top bar has arrows, Today, All Statuses, Month, Week and Day.
Fig. 18Month view. The order is on its date. The week starts on Sunday.
Order Details box. Work Order QA-6001, Status Closed, Item dash, Order Type Production, Order Qty 400, Built Qty 0, Due Date November 6th 2026, Description. Buttons Close and Edit Order.
Fig. 19Click an order to see its details. Edit Order opens the same Edit box as the list.
Good to know

The calendar week starts on Sunday. The This week and Next week tabs run Monday to Sunday. So an order due on a Sunday sits at the start of the calendar week but belongs to the week before it on the tabs.

You can drag an order to another day. That changes its Work Date, not its Due Date. The week tab it belongs to does not change.

The details box shows a dash under Item for a production order. The item is on the main list.

ExampleOrder QA-1001 is due Friday, November 6 and has no Work Date. In Month view it is on the 6th. You drag it to Monday the 9th to show it will be built then. The calendar shows it on the 9th, the Due Date is still the 6th, and it stays in This week on the tabs.

If something goes wrong

  • An order is missing from the calendar. Check the All Statuses filter, and make sure you are on the right month.
  • The search box on the Customer Orders tab hid orders. The calendar can follow it. Clear the search on the Customer Orders tab.