Beacon how-to · November 2026

Checkpoint: running a line on the tablet

Checkpoint is how a line tells Beacon what it built, when it stopped and who was on it. The line captain does it on the line tablet, from start of shift to close-out. This page has seven short how-tos, one for each job on the tablet. Do them in this order on a normal shift.

Known issues: read these first

Tap the first pallet soon after you startToday the labor clock starts at your first pallet tap, not when you press Start Line. Minutes before the first tap are not charged to the line. A fix is planned. Until then, tap the first pallet as soon as it is done.
The order must be on the Labor Planner tooAn order only shows in Start Line and Changeover if it is also placed on the Labor Planner, for today, on that line. If it is in the Build Schedule but not on the planner, it will not be offered. Ask the planner to place it.
Closing a line with 0 pallets gives no warningIf you close a line and the count is 0, Beacon does not stop you. Look at the numbers on the Close Out box before you confirm.

Screenshots are from Beacon's test site (shown as “Demo Site”). The orders QA-3101 and QA-3102 and every number are demo data, not real production data.

1. How to start a line

Who: line captain (or any lead) on the line tablet. When: when work starts on the line.

Before you start

  • Today's order is on the Labor Planner, on your line (see the known issues above).
  • You know how many people are working the order. You will be asked.

Steps

  1. On the tablet, go to Production and click Checkpoint Live.
  2. Find your line's card, for example 4B. It says READY and shows today's first order.
  3. Tap Start Line.
  4. The box Who's on this build? opens. Count the people standing in front of you now.
  5. Type that number in the Assembler box. The big button changes to, for example, Start build — 12 people.
  6. Tap that button. The console opens.
  7. When the first pallet is done, tap PALLET COMPLETE (see how-to 2).
The Who's on this build box for PO QA-3101, with 12 typed in the Assembler box and the button reading Start build, 12 people.
Fig. 1Type the crew in the Assembler box. The button shows the number back to you.
The line console for 4B. Current order PO QA-3101, today 0 of 300 cases, 27 cases per pallet. Today: 0 pallets, 0 cases, 0 minutes active. A large PALLET COMPLETE button below.
Fig. 2The console right after the start. Look at 27 cases/plt: that is what one tap will add.

Example

ExampleOrder QA-3101 is 300 cases. A pallet holds 27 cases, so the order is 11 full pallets and 3 loose cases, 12 pallets in all (300 ÷ 27 = 11.1). Twelve people are on the build. You type 12 and tap Start build — 12 people. The console shows Today: 0 / 300 cases and 27 cases/plt. The line card on the Checkpoint Live page now says RUNNING · YOU.

If something goes wrong

  • No Start Line button, or your order is missing. The order is not on the Labor Planner for today on this line. Ask the planner to place it. Do not use the grey Start Line (Off-Schedule) button for a normal order: it starts a line with no order and no crew question.
  • The start button stays grey. The crew box is 0 or has letters in it. Type a whole number, 1 or more.
  • You pressed Skip for now. The line starts with no crew count. Beacon does not ask again at close-out, so use the Crew button on the console to set the crew now.

2. How to count pallets on the tablet and undo a wrong tap

Who: line captain. When: every time a full pallet comes off the line.

Steps

  1. When a full pallet is done, tap the big PALLET COMPLETE button once.
  2. Look at the top of the screen. Today goes up by one pallet and by the cases on a pallet (for example +27).
  3. Wait a second or two before the next tap. Two fast taps count as one.
  4. If you tapped by mistake, scroll down a little and tap Undo last tap. It takes away the last tap.
Console after five taps. Today: 5 pallets, 135 cases, 0 minutes active. This hour: 135 of 125 cases, 108 percent pace.
Fig. 3Five taps: 5 pallets and 135 cases. This hour compares the cases with the hour's target (125) and shows the pace.
Console after one Undo. Today: 4 pallets, 108 cases. This hour: 108 of 125 cases, 86 percent pace.
Fig. 4After Undo last tap: back to 4 pallets and 108 cases.

Example

ExampleOrder QA-3101, 27 cases per pallet. You tap five times and the screen shows 5 pallets and 135 cases (5 × 27). The fifth pallet was not really done, so you tap Undo last tap. The screen now shows 4 pallets and 108 cases (4 × 27).

If something goes wrong

  • Taps do nothing. A downtime is running. Taps are ignored until you end it (how-to 4).
  • Each tap adds only +1 case. The material has no pallet size set. Tell the planner or the material master owner. Meanwhile, add the real cases with Partial pallet… (how-to 3).
  • You counted too many. Undo takes away the last tap, one at a time. Do not guess: count the pallets on the floor first.

3. How to enter loose cases

Who: line captain. When: cases are done but they do not make a full pallet (a part pallet at the end of an order).

Steps

  1. On the console, scroll down a little and tap Partial pallet… (a small link under Undo last tap).
  2. In the box Partial cases, type the number of loose cases.
  3. Tap Add cases.
The Partial cases box with 10 typed in the Loose cases field and an Add cases button.
Fig. 5Type only the loose cases. Do not type the pallets already counted.
Console after adding 10 loose cases. Today: 4 pallets, 118 cases, 118 of 300 for the order.
Fig. 6Cases go up to 118. The pallet count stays at 4.

Example

ExampleThe screen shows 4 pallets and 108 cases. Ten more cases are on a part pallet. You add 10 loose cases. The screen shows 4 pallets and 118 cases (108 + 10). The pallet count does not change, because a part pallet is not a pallet.

If something goes wrong

  • You typed a minus number. Beacon does not take it. To take cases away use Undo last tap for a pallet, or ask a coordinator to correct the day in Shift Review.
  • Cases were built before the tablet was connected. Use Built before connecting, just below, instead. Those cases count in the totals but not in the pace.

4. How to log downtime, lunch and break

Who: line captain. When: the line stops for a reason, or the crew goes to lunch or break.

Steps

  1. On the console, scroll down and tap DOWNTIME.
  2. Pick the reason: Mechanical, Material, Changeover, Break, Lunch or Other.
  3. A red bar appears at the top, for example DOWNTIME — MECHANICAL. The clock for the stop is running.
  4. When the line is running again, tap End Downtime.
  5. Beacon asks What happened? Type a short note, for example what you fixed. The note is optional. The coordinator sees it in Shift Review.
  6. Tap End Downtime in the box. The red bar goes away.
The Log Downtime box with six reasons: Mechanical, Material, Changeover, Break, Lunch, Other.
Fig. 7Six reasons. Pick the one that fits.
Console with a red bar reading Downtime, Mechanical, and an End Downtime button.
Fig. 8The red bar tells everyone the line is stopped.
The End Downtime Mechanical box with an optional note field for what happened.
Fig. 9The note is optional but helps the coordinator.
Console with a red bar reading Downtime, Lunch.
Fig. 10Lunch and Break work the same way. Pick them from the same list.

Example

ExampleAt 1:33 PM the infeed belt slips. You tap DOWNTIME → Mechanical. The bar says DOWNTIME — MECHANICAL. You tighten the belt, tap End Downtime, type Infeed belt slipped, tightened and restarted and tap End Downtime. A little later the crew goes to lunch: DOWNTIME → Lunch, and End Downtime when they are back. On this test site lunch is unpaid, so Beacon takes lunch minutes out of the labor hours.

If something goes wrong

  • The bar is still red after lunch. Someone forgot End Downtime. Pallet taps are ignored while it is red. Tap End Downtime and carry on.
  • You are changing to the next order. Do not log it as downtime. Use CHANGEOVER (how-to 5).

5. How to change over to the next order

Who: line captain. When: the line moves to the next order on the same shift.

Before you start

  • The next order is on the Labor Planner, on this line, for today. The CHANGEOVER button says 1 queued when one is waiting.

Steps

  1. On the console, scroll down and tap CHANGEOVER.
  2. The box Changeover lists the orders planned on this line. The order that is running now is not in the list.
  3. Tap LOAD next to the order you are starting.
  4. Count the crew for the new order and type it in the Assembler box.
  5. Tap Start build. The console now shows the new order.
  6. Wrap up the first order when it is done (how-to 6). A changeover does not do that for you.
The Changeover box listing PO QA-3102, 189 units, with a LOAD button. Below is Also run here and a note about orders that are not listed.
Fig. 11The next planned order and its planned units. The note at the bottom says an order must be scheduled on this line to appear.
Who's on this build box for PO QA-3102 with a Back button, Skip for now and Start build buttons.
Fig. 12Each order gets its own crew count.
Console for the new order PO QA-3102. Today 0 of 189 cases. Today across the line: 4 pallets and 118 cases.
Fig. 13The new order is running. The Today tile still shows the whole line's total.

Example

ExampleQA-3101 is at 118 cases. You tap CHANGEOVER and see QA-3102, 189 units. You tap LOAD, type 13 for the crew and start. The console shows QA-3102, Today: 0 / 189 cases. The line total at the top still says 4 pallets and 118 cases, because QA-3101's cases are still part of today.

If something goes wrong

  • The list is empty or your order is missing. The order is not on the Labor Planner for this line today. The box says the same in small print: it only shows orders scheduled on this line. Ask the planner.
  • Every tap adds only 1 case. The new material has no pallet size. See how-to 2.
  • You loaded the wrong order. Do not tap pallets. Tell a coordinator before you close out so they can correct it in Shift Review.

6. How to finish (wrap up) an order

Who: line captain. When: an order is done for today. The line keeps running on the next order.

Steps

  1. On the console, scroll down and tap WRAP UP PO. It says done for today and how many orders are still open.
  2. The box Which PO are you wrapping up? lists every order the line ran today, with its cases and its minutes on the line. Tap the order that is finished.
  3. Check the crew on the next screen. It shows the crew you typed when the build started.
  4. Tap Wrap up this PO. The line keeps running.
Which PO are you wrapping up. QA-3101 with 118 cases and 4 minutes on the line. QA-3102 with 3 cases and 0 minutes. The note says a changeover does not wrap up a PO.
Fig. 14Every order the line ran is listed. A changeover does not wrap up an order.
Wrap up this PO for QA-3101, 118 cases. Crew on this build: 12, 12 Assembler. Buttons Back, Cancel and Wrap up this PO.
Fig. 15The last check: the order, its cases and its crew.

Example

ExampleThe line ran QA-3101 (118 cases, 4 minutes) and then QA-3102 (3 cases). QA-3101 is finished, so you tap WRAP UP PO and then QA-3101. The crew shows 12. You tap Wrap up this PO. The button now says 1 open, and END SHIFT says 1 PO will be wrapped up too.

If something goes wrong

  • You forgot to wrap up an order. END SHIFT wraps up the orders still open. If you close the line without it, Shift Review lists the order and a coordinator finishes it there.
  • You picked the wrong order. Tap Back or Cancel before you confirm.

7. How to close out a line at the end of the shift

Who: line captain. When: the last order is done and the line stops for the day.

Before you start

  • All downtime is ended (no red bar).
  • You know the real pallet count for the shift. Beacon does not warn you if it is 0.

Steps

  1. On the console, scroll down and tap END SHIFT.
  2. The Close Out box shows cases today, Pallets today and Active time (measured), and the time the line ended.
  3. Read the numbers. If they are wrong, tap Cancel and fix them first.
  4. Tap Confirm Close Out.
  5. The screen says 4B — Closed for today with the totals and the headcount. Nothing on it can be tapped. Tap Back to Connect to leave.
The Close Out box: 121 cases today, 7 pallets today, active time 4 minutes, line ended at 1:35 PM. Cancel and Confirm Close Out buttons.
Fig. 16Check these three numbers before you confirm.
4B Closed for today. Cases 121, Pallets 7, Active time 4 min, Headcount 13. A note says a coordinator reviews it in the shift review.
Fig. 17The line is closed. The coordinator reviews it next in Shift Review.

Example

ExampleLine 4B built 118 cases of QA-3101 (4 pallets) and 3 cases of QA-3102 (3 taps of 1 case, because that material had no pallet size). The Close Out box says 121 cases, 7 pallets, 4 minutes active (121 = 118 + 3 and 7 = 4 + 3). You confirm. The closed screen shows the same numbers and a headcount of 13.

If something goes wrong

  • Pallets today shows 0. Beacon will still let you confirm. Do not. Count the floor and tap the pallets first, or ask your coordinator.
  • Active time is very short. The clock starts at the first pallet tap (see the known issues). Tap the first pallet soon after you start a line next time.
  • You closed too early. Tell your coordinator. They can reopen the line in Shift Review. See Shift Review how-tos and Fix a shift.