Beacon how-to · November 2026

Fix counts, lunch and downtime in Shift Review

A coordinator can now fix a PO's units and pallets, add a lunch or break nobody tapped, add a run that was never started on the tablet, and take back a stop that was logged by mistake, right in the Close Out box. Every fix keeps the measured number, your name and your reason.

  • v2.180.0
  • Remove or change logged downtime: v2.188.0
  • Line's hours start at Start Line: v2.192.1

Screenshots are from Beacon's test site. POs DEMO-2241 to DEMO-2294 and DEMO-4A are demo data, not real production numbers.

1. What's new

The coordinator's Close Out box (Close & adjust here, or Reopen then close on a closed line) has four new parts:

  • Counts per PO. One row per PO, with the measured units and pallets and a box beside each.
  • Downtime. Add a lunch, break or other stop that nobody tapped on the tablet.
  • Missed runs. Add a PO that ran but was never started on the tablet, with its times, crew, units and pallets.
  • Logged downtime. New. Remove a stop that was logged by mistake, lower its minutes, or change its reason. How
  • Reason for the fix. Required as soon as you change anything.
ExampleLine 1A shows PO DEMO-2241 from 7:15 to 3:25 with 532 units. Really, DEMO-2241 built 360 and stopped at 1:25, PO DEMO-2292 ran 1:25 to 3:25 with 14 people and built 272, and nobody logged lunch. In one Close Out: type 360 for DEMO-2241, add the missed run DEMO-2292, 1:25–3:25 PM, 13 + 1 crew, 272 units, 4 pallets, add Lunch at 11:30 for 30 minutes, give a reason, confirm, then re-post. DEMO-2241 posts 360 cases and 81.05 hours; DEMO-2292 posts 272 cases and 26.29 hours.

2. Who can fix, and for how long

  • Coordinators, Admins and Super Admins. Leads still see measured counts only at End Shift.
  • Only on a day that isn't submitted. If it is, click Reopen day for correction at the bottom of Shift Review first, with a reason.
  • Ferrara: 48 hours. A coordinator can fix a day until 48 hours after that day ends. A Monday shift can be fixed until the end of Wednesday. After that, the boxes are hidden and the page says “Past the 48-hour fix window. An Admin can still fix this day.” An Admin can still fix it, with a reason.

3. Fix units or pallets on a PO

  1. Open the line's Close Out: Close & adjust here for a line still running, or Reopen at the right end of a closed line's row, then Close & adjust here.
  2. Under Counts per PO, type the right number in the PO's Units or Pallets box. Leave a box empty to keep the measured number.
  3. Check units today and Pallets today under the rows. They add up the rows, so you never type a line total.
  4. Type the Reason for the fix and click Confirm Close Out.
  5. Click Submit Shift Review, or Re-post day on a reopened day.
Close Out box, Counts per PO: PO DEMO-2243 units 86, pallets 4; PO DEMO-2244 units 78, pallets measured 5 with 4 typed. Units today 164, pallets today 8. Below, a Break at 9:00 AM for 15 minutes, and the reason: afternoon break not tapped; DEMO-2244 last pallet tapped twice.
Fig. 1A line with two POs. DEMO-2244's pallets go from 5 to 4, and Pallets today follows to 8. Demo data.
Good to knowUnits that belong to no PO show as a grey “Not tied to a PO” row so the total still adds up. Clearing a box you typed before puts the measured number back. A PO typed to 0 that still has run time posts the whole line at its peak crew; the box warns you.

4. Add a lunch or break nobody tapped

Line status strip before any fix: 1A Lunch not logged in amber, Breaks 1, 15 min, paid, with an Add lunch button. 1B Lunch 30 unpaid, Breaks 1, 15 min, paid. 4A Lunch not logged in amber, Breaks not logged, with Add lunch and Add break buttons.
Fig. 2The strip above the table, on a reopened day. Lines with no Lunch or Break get Add buttons. Demo data.
  1. In the line status strip above the table, click Add lunch or Add break on a closed line. The Close Out box opens with Lunch 30 or Break 15 filled in. (You can also click + Add downtime in any Close Out.)
  2. Type the Start time. Change the minutes if they were different. Add a note if it helps.
  3. Type the Reason for the fix, click Confirm Close Out, then submit or re-post.
Close Out box for line 1A: PO DEMO-2241 units 532 measured, 360 typed, pallets 14. Units today 360. Downtime: Lunch, start 11:30 AM, 30 minutes, note not tapped on the tablet. Reason for the fix: lead tapped 532, floor count was 360; lunch not logged.
Fig. 3The Nov 2 kind of fix in one box: the count and the missed lunch together. Demo data.
Don't take lunch off twiceIf you add Lunch here, leave Active time as measured. Lunch comes off the posted hours by itself, at most 30 minutes a day. Breaks are paid: adding one changes efficiency, not pay.

The box refuses a stop outside the line's hours (“Downtime must be inside the line's hours (7:00 AM to 3:00 PM)”) and warns when the time overlaps downtime already logged.

The line's hours start at Start Line (v2.192.1)

The line's hours run from Start Line to the end the box shows. That is the same start the Active time is measured from. Before this fix they started at the first pallet tap, so a lunch taken before anyone tapped was refused.

ExampleA line was started at 7:42 AM, but nobody tapped a pallet until 11:58 AM. It ended at 3:21 PM: 459 active minutes. Lunch was 11:12 to 11:42. The box used to say “Downtime must be inside the line's hours (11:58 AM to 3:21 PM)”, several times over. Now Lunch at 11:12 for 30 minutes goes in, and it comes off the posted hours like any other lunch.
Close Out box for demo line 4A. Downtime: Lunch, start 11:12 AM, 30 minutes. Reason for the fix: Lunch 11:12 to 11:42. No red message. Line ended at 3:21 PM (last pallet). Ended at 3:21 PM. Active time 459, measured 7h 39m.
Fig. 3aLunch at 11:12, before the first tap at 11:58, goes in on a line started at 7:42. Demo data (PO DEMO-4A).
The same Close Out box with Lunch moved to 7:30 AM. One red line: Downtime must be inside the line's hours (7:42 AM to 3:21 PM). Active time 459, measured 7h 39m.
Fig. 3bA stop before Start Line is still refused. It says so once, with the real hours. Demo data.
After Confirm Close Out. Changeovers: 4A, No changeovers, Lunch 30 min. Corrections on this day: 4A by Claude Demo, Lunch 30 min at 11:12 AM (11:00 AM hour 30). Reason: Lunch 11:12 to 11:42.
Fig. 3cAfter Confirm: 4A shows Lunch 30 min, and the fix is listed in Corrections on this day. Demo data.
Good to knowWhere the lunch sits on the clock does not change pay. Posted hours take the lunch off the line's total and share it across the crews by how long each one ran. A stop before Start Line, or after the line's end, is still refused. The start-up window before Start Line is not line hours.

5. Remove or change logged downtime

A stop logged by mistake can now come back off. In the same Close Out box, under Counts per PO, a Logged downtime list shows every stop on the line, one row for each hour and reason: “8:00 AM · Other 25” or “11:00 AM · Break 33 — 15 Minute Break”. Each row has three things you can do:

ToDo this
Take it offClick Remove. The minutes go to 0.
Lower itType a smaller number in Minutes. To add minutes, use + Add downtime: it is the one way to add, so a stop is never booked twice.
Change the reasonPick another Reason. The minutes and the note come along. Changeover is not on the list (tap CHANGEOVER on the tablet, or use Add changeover). A Changeover stop logged before v2.185.0 can be changed to another reason.
  1. Open the line's Close Out: Close & adjust here for a line still running, or Reopen at the right end of a closed line's row, then Close & adjust here. (The Add lunch button opens it on a closed line too.)
  2. Under Logged downtime, click Remove, type a smaller number, or pick another reason. Undo puts a row back.
  3. Read the amber lines under the reason box. They say what the fix will move, before you confirm it (see below).
  4. Type the Reason for the fix and click Confirm Close Out. Then submit, or re-post the day.
Close Out box, Logged downtime, line 1A. Take downtime off, lower its minutes, or change its reason. To add minutes, use Add downtime below. Four rows. 9:00 AM Break 18, 15 Minute Break: Minutes typed 3, Reason Break, Remove and Undo. 11:00 AM Break 33, 15 Minute Break: Minutes typed 18, Reason Break, Remove and Undo. 11:00 AM Lunch 22 and 12:00 PM Lunch 8, untouched.
Fig. 4Line 1A logged two scheduled breaks as downtime. They are typed down to 3 and 18. The two Lunch rows are listed too, and left as they are. Demo data.
Example: downtime logged on top of a changeover

Line 6B tapped CHANGEOVER at 8:06, and the next PO's first pallet came at 8:30. The changeover ran 17 minutes. The crew also logged 25 minutes of Other. Downtime wins the minute, so Beacon counted the changeover as 0. Click Remove on “8:00 AM · Other 25” (Fig. 5). Once you confirm, the changeover reads 17 min (Fig. 6), the warning on Shift Review is gone, and that hour's Downtime is 0. See Downtime during a changeover.

Close Out box for line 6B. Add changeover: 8:06 AM, PO DEMO-6B-A to PO DEMO-6B-B, measured 0 min. Logged downtime: 8:00 AM Other 25, struck through, Minutes 0, Reason Other, Remove greyed, Undo. 12:00 PM Lunch 30, untouched. Reason for the fix: Other 25 was the changeover, logged twice. In amber: 6B's changeover into PO DEMO-6B-B will count 17 min.
Fig. 5The Other 25 is struck out. The amber line says what the changeover will count. Demo data.
Close Out box, Add changeover, after the fix: 8:06 AM, PO DEMO-6B-A to PO DEMO-6B-B, measured 17 min. PO DEMO-6B-A ran 7:38 AM to 8:06 AM. PO DEMO-6B-B ran 8:30 AM to 3:00 PM.
Fig. 6The same changeover the next time the box is opened: 17 minutes, where it read 0 before. Demo data.

What the box warns you about

These are warnings, not stops. Nothing is saved until you confirm.

You take off…The box says
A Lunch, at a site that does not pay Lunch (Ferrara)“Lunch: 30 min come off pay now, 0 after this fix. These minutes go back on pay.” Posted hours go up by those minutes when you re-post. Only 30 minutes a day come off pay, so lowering a 45 minute Lunch to 35 changes no pay and shows no warning.
Downtime that was inside a changeover“6B's changeover into PO DEMO-6B-B will count 17 min.”
Downtime that sat in an idle gap between two runs“40 min of this downtime sat in an idle gap between runs. Without it that gap is idle time, so active (paid) time drops by 40 min.”
Logged downtime for line 6B with both rows struck out: 8:00 AM Other 25 and 12:00 PM Lunch 30, Minutes 0. Reason for the fix: Other 25 was the changeover, logged twice. Two amber lines: Lunch, 30 min come off pay now, 0 after this fix, these minutes go back on pay. 6B's changeover into PO DEMO-6B-B will count 17 min.
Fig. 7Taking off the Lunch as well: both warnings show. Demo data.

Good to know

  • If the hour changed while you were in the box (the lead logged more downtime in that hour), Confirm Close Out refuses: “8:00 AM on 4A changed since you opened this. Close and open the dialog again.” Nothing is saved. Close the box, open it again and redo the fix, so you never wipe a stop you did not see.
  • An old hour that mixes reasons and was never split (“Mechanical; Material 20”) is one row. You can remove it, or change all of it to one reason. You can't lower just part of it.
  • Minutes logged with no reason (a stop on the tablet where nobody picked one) are their own row, “9:00 AM · No reason 10”, next to the hour's other rows. Pay counts them as neither Lunch nor Break, so the list never files them under one. Remove them, or pick the reason they were. If you add a Lunch to that hour, the Lunch is its own row and the 10 stays a “No reason” row.
  • One Confirm can do both. You can fix a logged stop and add a missed Lunch in the same box. The fix is applied first, and the amber lines already count what you add: remove a Lunch 45 and add a Lunch 30 and the box does not claim pay changes.
  • Same rules as every fix: Coordinator and up, inside the fix window, on a day that is not submitted, with a reason.
Close Out box for line 4A with a reason change pending on 8:00 AM Other 25, waited on forklift, and a Lunch of 30 minutes at 12:00 PM added. A red message: Couldn't save the fixes. 8:00 AM on 4A changed since you opened this. Close and open the dialog again.
Fig. 8Five more minutes were logged in the 8:00 hour after the box was opened, so the save is refused. Demo data.

Where it shows

  • The line's Downtime column and notes drop by what you took off. Closed POs' downtime is worked out again, so Actual Run Time follows.
  • Corrections on this day lists each change with your name, the time and your reason (Fig. 9).
  • Fixes this week in the Weekly Synopsis, and the weekly email, count it as a downtime fix and say what you did (Fig. 10).
  • Posted hours change only when you re-post the day.
Corrections on this day. 6B at 12:13 AM by Claude Demo: 8:00 AM Other 25 to removed. Reason: Other 25 was the changeover, logged twice. 1A at 12:16 AM: 9:00 AM Break 18 to 3, 11:00 AM Break 33 to 18. Reason: Scheduled breaks were logged as downtime. 4A at 12:21 AM: 8:00 AM Other to Mechanical, Lunch 30 min at 12:00 PM. Reason: It was a filler jam, and lunch was missing.
Fig. 9One entry per Confirm: “removed”, “18 → 3” for a lowered stop, “Other → Mechanical” for a new reason. Demo data.
Fixes this week. Line 4A fixed on 2 of 7 days: 2 downtime, 1 changeover. 1A fixed on 1 of 7 days: 2 downtime, 9:00 AM Break 18 to 3 and 11:00 AM Break 33 to 18. 6B fixed on 1 of 7 days: 1 downtime, 8:00 AM Other 25 to removed. Who and why on the right.
Fig. 10Fixes this week. A Lead sees only a note that these are shown to coordinators. Demo data.

6. Lunch and Break on every line

The strip above the table shows, for every line, whether Lunch and Break were logged and which one is paid. A missing Lunch is amber because it changes pay. A missing Break is plain. Each downtime shows with the note typed on the tablet.

A line that ran 5 hours or more with no Lunch also gets a row under Check before you submit, with an Add lunch button. It never stops Submit.

Check before you submit, these don't stop Submit: Census, lines had 33 people working at once, the census says 29. 1A ran 8h 10m with no Lunch logged, Add lunch. 4A ran 8h 0m with no Lunch logged, Add lunch.
Fig. 11A missed Lunch is listed before you submit. Demo data.
Line status strip after the fix: 1A Lunch 30 unpaid (30 off pay), Breaks 1, 15 min, paid, Downtime Break 15 and Lunch 30. 1B the same. 4A Lunch not logged in amber, Breaks not logged, with Add lunch and Add break. Below, Corrections on this day: 1A at 11:42 AM by Claude Demo, PO DEMO-2241 units 532 to 360, Lunch 30 min at 11:30 AM, and the reason.
Fig. 12After the fixes: the strip, and the Corrections on this day list with who, when, what and why. Demo data.

7. Add a run nobody started

Use this when a PO really ran on a line but the lead never started it on the tablet (for example the PO wasn't in the Changeover list).

  1. Open the line's Close Out (Reopen then Close & adjust here, or an Add lunch button). Click Add a missed run.
  2. Pick the PO from this week's plan (or Other PO… to type it and pick the SKU). Type Run start, Run end, the units and pallets the run built, and the crew by role.
  3. Check the Before and After lines. The PO that was showing on the tablet then gives up that time. If it carried on after the missed run, leave The PO it overlaps ran again after this ticked.
  4. If that PO's own count was wrong too, type it in its Counts row (the box shows what Beacon measures once the run is in). Give a reason, confirm, then submit or re-post.
Missed run entry: PO DEMO-2292, run start 1:25 PM, run end 3:25 PM, 272 units, 4 pallets, crew Assembler 13 and Temp 1, 14 total, and The PO it overlaps ran again after this ticked. Below: Before 7:15 AM to 3:25 PM PO DEMO-2241. After 7:15 AM to 1:25 PM PO DEMO-2241, 1:25 PM to 3:25 PM PO DEMO-2292 (added). PO DEMO-2241: 532 to 446 units measured.
Fig. 13The missed run, with the line before and after. The units tapped on DEMO-2241 while DEMO-2292 was really running move to the added run. Demo data.

A line that never started at all (it shows Never started): under the Corrections list, pick the line in Add a run on a line that didn't start and click Add run. The same Close Out opens with one empty run. Nothing is saved until you confirm.

Corrections on this day. 1A at 12:26 PM by Claude Demo: Added run PO DEMO-2292 1:25 PM to 3:25 PM, 14 people, 272 units, 4 pallets. PO DEMO-2241 now ends 1:25 PM. PO DEMO-2241 units 446 to 360. Lunch 30 min at 11:30 AM. 4B at 12:30 PM: Added run PO DEMO-2294 7:00 AM to 11:00 AM, 9 people, 120 units, 3 pallets.
Fig. 14Both kinds in the Corrections list: a run added inside another PO's time on 1A, and a whole run on 4B, a line that never started. Demo data.
Good to knowHours follow the runs: each run's crew × its own minutes. Pallets never move between POs. You can't move or delete a run that was started on the tablet; add the right one over it instead, and it takes that time.

8. What changes when you confirm

  • The posted numbers change at Submit or Re-post day, not before. Each PO posts the units and pallets you typed.
  • Hours: an added Lunch comes off the line's posted hours (crew × minutes, at most 30 a day). A Lunch you remove goes back on pay. A count fix doesn't change hours.
  • The measured number is kept beside the typed one, and the hourly strip stays as measured. That is why a corrected line's hours no longer add up to its total; the Corrections list says why.
  • Every fix is recorded with your name, the time, the reason, and the before and after. Nobody can edit or delete that record.
  • Lines you don't touch post exactly as before.