Beacon how-to · October 2026

What's new: v2.168.0

Beacon can now keep the plan as it stood before the shift and show how each order did against it. A site can also let Beacon close out the day on its own. Both are off until an Admin turns them on.

  • v2.168.0

1. Patch notes

v2.168.0 Oct 29, 2026

  • Plan vs Actual tracking in Settings → Shift Window. An Admin starts it. Each planned block is frozen before its shift, so later edits never rewrite what the plan was. How to start it
  • Re-baseline. When the old plan is no longer fair, a Coordinator can make the current plan the new target for one order or one day, from today on, with a reason. How
  • Shift Review Submit grades each planned order: on plan, ahead or short, with hours earned against hours worked. Grading never blocks Submit. What happens
  • New Analytics → Plan vs Actual tab. The last 4 weeks plus this week, a verdict per order, hours by role, margin vs plan for Leads and up, and a CSV export. Read the tab
  • Automatic close-out in Settings → Email. Off for every site until an Admin turns it on. At the cutoff, Beacon closes open lines at their last pallet, submits Shift Review, posts the hours and emails the synopsis. How it works
  • Shift Review and Checkpoint times now show in the site's time zone, not the device's. Example
  • Checkpoint Today tile: tapped cases show beside pallets, and a starting count shows as its own part. See it

Screenshots are from Beacon's test site. PO numbers and figures are demo data, not real production numbers. They were taken before the release, so the version badge in them reads v2.167.0.

2. Start Plan vs Actual

Who does it: an Admin, once per site. Nothing changes on the floor until it is started.

The planner changes all day. Orders get cut, moved and added. Without a saved copy, nobody can say later what the plan was. Tracking keeps that copy.

  1. Go to Admin → Settings → Labor Planner → Shift Window.
  2. Under Plan vs Actual tracking, set Freeze hours: how many hours before its start a planned block is frozen.
  3. Click Start tracking, then Start tracking again in the box that opens.
Settings, Shift Window card. Plan vs Actual tracking: Not tracking. Freeze hours 24, and a Start tracking button.
Fig. 1Before tracking starts. Freeze hours was set to 24 for the demo.
Confirm box: Start Plan vs Actual tracking. From now on, each planned block is recorded when it freezes, and later changes count as off plan. Blocks that froze earlier are never graded. This cannot be switched off here.
Fig. 2Once started, tracking stays on. Settings then reads “Tracking since” and the date.
ExampleFreeze hours is 16.5. A block that starts Friday at 7:00 am is frozen Thursday at 2:30 pm. If someone cuts it from 800 to 400 on Thursday night, the plan Beacon grades against still says 800.

On the Labor Planner, a frozen block shows a small lock. Hover over it to see when it froze. Edits after that count as off plan.

Labor Planner, Friday October 30, lane 1A. The first block, 60170136 PO 1063438 crew 13, has a lock. A later block has no lock yet.
Fig. 3Lane 1A on the test site: the first block is frozen (lock), the later one is not yet. Demo data.

3. Re-baseline a plan

Who does it: a Coordinator or above.

Sometimes the frozen plan is no longer a fair target. The customer cancels half an order, or pulls one off the day. Re-baseline makes the current plan the new target, so the line is not graded “short” for work nobody wanted.

  1. Open the day on the Labor Planner and click Re-baseline (next to Clear day).
  2. Pick This day or One order. For one order, choose the PO.
  3. Type the reason. It is required, and it shows on the Plan vs Actual tab.
  4. Click Re-baseline.
Re-baseline the frozen plan, with This day (Fri, 10/30) picked. 2 frozen blocks will take the current plan as the new target. Reason box filled in. The same box with One order picked and order 1063433 chosen. 1 frozen block will take the current plan as the new target.
Fig. 4Left: the whole day. Right: one order. Demo data.
ExampleThe customer cuts a PO from 800 to 400 the day before. The planner is changed to 400, but the frozen plan still says 800. Re-baseline that order with the reason “Customer cut the order to 400”. Now 400 built grades on plan, not short 400.

Re-baseline works from today on only. Past days keep the plan they were graded against. You can also re-baseline one PO from its row on the Plan vs Actual tab, with Re-baseline this PO.

4. Submit grades the day

Nothing new to do here. Close out and submit Shift Review the way you do now. When you click Submit, Beacon grades each planned order against its frozen plan:

  • On plan built what the plan asked for.
  • Ahead built it earlier than planned.
  • Short built less than planned, and by how many.

It also compares hours earned (what the cases built are worth at standard) with hours worked (crew × time).

Shift Review for 10/29/2026. Line 1A closed, 200 actual units against 500 planned units, 40 percent attainment. Other lines never started.
Fig. 5Line 1A built 200 of 500 planned. On Submit, the first order (200 of 200) graded on plan and the second (0 of 300) graded short. Demo data.

The grades show on the Plan vs Actual tab, not on Shift Review. If grading ever fails, Submit still goes through, and a message says the day could not be graded.

Not graded yetDays submitted by automatic close-out are not graded for Plan vs Actual yet. Days a person submits are.

5. The Plan vs Actual tab

Go to Analytics → Analytics → Plan vs Actual. It shows the last 4 weeks plus this week. This week counts submitted days only, up to today.

The four cards

  • Volume: cases built out of cases planned.
  • Hours: hours worked against the standard for what was built.
  • Units per person-hour: the pace, as a percent of standard.
  • Margin: revenue minus labor, against plan. Leads and up only.
Analytics, Plan vs Actual tab. Cards: Volume 87 percent of planned cases, Hours over standard by 10.2 h, Units per person-hour 94 percent of standard pace, Margin 9,797 dollars. Below, a table of demo POs grouped by week with plan, built percent, hours vs standard and a verdict.
Fig. 6The tab on the test site. POs named DEMO-PVA are demo data.

Verdict per order

Each order gets a verdict, for example Short 200 cases, Ahead of schedule, Late 2 working days, Over standard by 1.0 h, Unplanned extra or Changed inside the freeze. A re-baselined order shows its reason.

Use the chips above the table (Short, Over standard, Late) to see only those orders, or search by PO or SKU.

Drill down

Click an order to open it. You see it day by day, and hours by role: planned against actual for Assembler, Line Captain and so on.

DEMO-PVA-107 opened: Thursday 10/29, plan 500, built 300, plan hours 50.0, actual 30.6, earned 30.0, grade Short 200 cases, Changed inside the freeze. Hours by role: Assembler 45.0 planned, 27.5 actual; Line Captain 5.0 planned, 3.1 actual. Revenue, labor and margin on the right, and a Re-baseline this PO button.
Fig. 7DEMO-PVA-107: 300 of 500 built, short 200, with hours by role. Demo data.

Who sees money

Margin and dollars show to Leads and up only. Cost-plus sites see no money at all: the Margin card and the dollars are gone, and everything else stays.

The same tab on a cost-plus site: three cards, Volume, Hours and Units per person-hour. No Margin card.
Fig. 8The same demo data on a cost-plus site. No Margin card.

Export

Click Export to download what is on screen as a CSV file you can open in Excel.

6. Automatic close-out

Off for every site. Nothing happens until an Admin turns it on for the site.

Some days nobody closes the lines or submits Shift Review before going home. Then the hours are not posted and the synopsis email never goes out. Automatic close-out does it at a set time.

Turn it on

  1. Go to Admin → Settings and scroll to the Email settings.
  2. In the Automatic close-out card, switch it on.
  3. Set Time (site time) and pick the days.
  4. Click Save Automatic Close-out.
Automatic close-out card, switched on. Time (site time) 05:15 PM. Monday to Friday picked, Saturday and Sunday not. Save Automatic Close-out button.
Fig. 9On the Ferrara test site: 5:15 pm, Monday to Friday. Demo settings.

What it does at the cutoff

  1. Closes any line still open at its last pallet, not at the cutoff. Idle time after the last pallet is not counted.
  2. Submits Shift Review if nobody has. It is signed Beacon (automatic).
  3. Posts the hours, the same as when a person submits.
  4. Emails the Daily Synopsis to the site's list, with a note at the top that it was automatic.
ExampleCutoff is 5:15 pm. Line 4A is still open, and its last pallet was tapped at 5:02 pm. At 5:16 pm Beacon closes 4A at 5:02 pm, submits Shift Review and emails the synopsis. The 13 minutes after the last pallet are not posted.
Checkpoint console: 4A Closed for today. Cases 231, Pallets 3, Active time 2 min, Headcount 10.
Fig. 10A console left open on the line switches to “Closed for today”. Demo data.
Shift Review 10/29/2026. Banner: Auto-submitted at 5:16 PM, 1 line auto-closed. 4A Auto-closed at 5:02 PM (last pallet). Line 4A closed with 231 units.
Fig. 11Shift Review shows what was closed automatically, and when. PO ADR213DEMO is demo data.
Top of the Daily Synopsis email: Auto-submitted by Beacon at 5:16 PM CDT. 1 line was still open and was closed at its last recorded activity: 4A (5:02 PM, last pallet). Shift Hours was blank, so the measured run time (0.03h) was used.
Fig. 12The note at the top of the email. From a test run; the email went to a test inbox only.

When it leaves the day for a person

  • If a line was started after the cutoff, Beacon leaves that day alone. A person closes out and submits as usual.
  • If someone already submitted Shift Review, Beacon does not submit again.
Plan vs ActualDays submitted automatically are not graded for Plan vs Actual yet. If your site uses both, submit by hand when you can.

7. Times in the site's time zone

Times of day on Shift Review and Checkpoint now follow the site's time zone, not the zone the computer or tablet is set to.

ExampleFerrara is on Central time. A laptop set to Eastern time used to show a 5:16 pm submit as “6:16 PM”. It now shows 5:16 PM, the same as the floor clock and the email.

No screenshot for this one. There is nothing to set: the site's time zone is already in Beacon.

8. Today tile: starting count

On the Checkpoint console, the Today tile shows pallets, then the cases you tapped today. If the line has a starting count (cases built before connecting), it shows under the cases as + N starting. It is no longer mixed into the tapped total.

ExampleLine 4A entered 144 cases built before connecting, then tapped 44 pallets of 36 cases. The tile reads 44 pallets, 1,584 cases, + 144 starting. 44 × 36 = 1,584, so the numbers now add up.
Checkpoint console for line 4A, PO DEMO-1103006. Today tile: 44 pallets, 1,584 Cases plus 144 starting, 249 min active. Current order: Today 1,728 of 2,000 cases.
Fig. 13Today tile with a starting count. PO DEMO-1103006 is demo data.

The Close Out sheet shows it the same way.

Close Out sheet: cases today 1,584 plus 144 starting. Pallets today 44. Active time (measured) 249 min.
Fig. 14Close Out: 1,584 tapped + 144 starting. Demo data.

The order's total still counts the starting cases: Today: 1,728 / 2,000 on the console, and the day total on the line board. Rates and pace leave them out, as before.